Council officers are recommending pulling the plug on the planned £2.35m Stornoway Primary Sports Hall in favour of a complete rethink after pupil numbers at the school plunged 37% in only six years .
Plans for the long-awaited sports hall development were derailed after the council failed to secure a Building Warrant due to wrangling over crucial building safety guarantees.
The dispute, which lasted nearly two years, was over the use of specialised materials in the development’s construction and led to the procurement contract being pulled in September.
Now, the education service is advising councillors meeting on Tuesday (November 24) to go back to the drawing board.
The sports hall’s specialised tensile fabric structure involved a 565-square-metre aluminium-framed and insulated tensile fabric building — roughly equivalent to three to four badminton courts — aimed at resolving severe overcrowding in the school’s physical education and dining spaces.
Planning permission was granted in December 2024. But the project ground to a halt due to need for a Building Warrant. As non-standard building materials had been chosen, a detailed technical check was required by the Scottish Building Standards Hub. This was a process that took considerably longer than expected.
However, negotiations with the single preferred supplier capable of delivering the design broke down when safety assurances could not be provided.
In a report prepared for the Comhairle’s Education, Sport and Children’s Services Committee meeting, Donald Macleod, Chief Officer for Education and Children’s Services, confirmed that "no guarantees could be obtained from the supplier that their building could meet the requirements to grant the Building Warrant".
As a result, the procurement process and associated contracts were formally terminated.
The cancellation comes after years of spiralling cost estimates. Initially approved in principle in November 2021 with a maximum construction budget of £1.8 million, the price tag rose to £1.95 million in 2022, £2.25 million in 2024, and finally hit £2.35 million in February 2025.
To cover the funding gap, the Comhairle topped up its core £2 million capital allocation with £350,000 from the Scottish Government’s Universal Free School Meals Expansion Programme, reflecting plans for the sports hall to double as extra lunchroom space.
Despite the rethink, council officials confirm there will be ring-fencing of the £2 million capital and the £350,000 for dining while a fresh plan is drawn up.
While technical hurdles triggered the contract termination, officials point out that the school's circumstances have altered dramatically since the sports hall was first proposed in 2021.
The most striking change is a sustained 37 per cent drop in the school roll between 2020 and 2026, a loss of 170 pupils.
This slump in pupil numbers has seen the number of primary classes drop from 20 down to 15, significantly easing timetable pressures.
Previously, delivering the mandatory two hours of physical education required 40 hours of gym time per week. With only a 147-square-metre gymnasium available, 15 hours of PE had to be shoehorned into the 202-square-metre assembly hall, creating friction with daily lunch services.
Today, overall PE demand has fallen to 30 hours per week, reducing assembly hall PE usage to just five hours.
The physical layout of the school grounds has also evolved in the meantime. Five classrooms inside the main building were recently remodelled to create a new Early Learning and Childcare (ELC) centre with three playrooms, reducing overall primary classroom capacity.
Outdoors, the addition of nursery facilities, a polycrub, and a community garden area has reduced the total outdoor play space available to pupils.
Community opinions on what facilities are actually needed remain divided, councillors will hear. Historically, parents had campaigned for an all-weather pitch or Multi-Use Games Area (MUGA) because the school’s grass playing fields are frequently waterlogged and unplayable for long stretches of the year.
The report notes that "representations continue to be made that the greater priority for facilities at the school is for year-round outdoor play space instead of, or in addition to, indoor PE facilities".
Future demand could also be influenced by two major housing developments currently under construction within the Stornoway Primary catchment area, comprising 254 new homes.
While past developments have tended to shift existing residents around rather than spark a net surge in pupil enrolments, the impact on Stornoway Primary remains uncertain.
Meanwhile, the new Scottish Government curriculum for ages 3–18 could further change requirements. Rather than rush into another build, council officers recommend going back to the drawing board.
Donald Macleod states in his report that "time should be taken to reassess and carefully plan for a new approach that will secure a deliverable project".
He adds that "it is considered prudent and responsible to reassess the requirements of the school for leisure and sports facilities so that a new proposal can be taken forward that best meets the needs of the current and projected school population".
The Education, Sport and Children’s Services Committee is being asked to commission a technical update to the school’s 2018 Site, Accommodation and Capacity Report, and to incorporate the sports project into a wider, council-wide School Estate Review approved in September 2026.