A lack of commercial interest in the Western Isles EV charging network is forcing Comhairle nan Eilean Siar to foot the bill while charge points continue to be partially powered by diesel generators.

A major HITRANS business case has revealed that national policies to attract private capital into public EV networks have broken down in the Western Isles. Commercial energy companies are abandoning investment in an electric vehicle charging network. This is being attributed to low usage forecasts and financial risk.

Now, council officers are warning the Transportation and Infrastructure Committee that the Comhairle will be saddled with the bill or risk putting the brakes on island-wide decarbonisation.

Under Transport Scotland’s national EVIF framework, Scottish local authorities were tasked with securing £30 million in private sector capital alongside £30 million in public grants to expand charging infrastructure rapidly. 

However, the business case by the Highlands and Islands transport body makes it plain that private operators see no commercial future for them in the Western Isles.

Addressing the complete lack of private appetite, the council update report states that “early market engagement noted some interest, but this has since been withdrawn, which is consistent with observations across the market, particularly related to risk appetite and sensitivity around a reliance on projected increases in utilisation to provide a return.”

The Scottish Futures Trust (SFT) have agreed with this assessment, stating that “leveraging private sector investment through a “traditional” EVIF concession-type contract does not appear to be immediately viable for the North West Scotland initiative at this time.”

The SFT added that “forecasted utilisation is accepted as being comparatively low and it would be unlikely any private sector operator or investor would see an acceptable level of return.” This retreat from the islands is due to low EV ownership and minimal charge point usage.

Pure battery electric vehicles (BEVs) are the lowest proportion in the regional partnership, falling well below the Scottish average of 3.4%.

Furthermore, local public AC chargers sit well below the lowest target threshold expected by the SFT.

Paradoxically, island drivers depend far more on public charge points than commuters elsewhere in Scotland. An estimated 26% of all EV charging energy consumed in the Western Isles is drawn directly from the council’s public network, the highest proportion in the HITRANS region.

This reliance is driven by island housing constraints, where 15–20% of households have no off-street parking, and many face severe hurdles installing smart meters.

With commercial operators walking away, the Comhairle must step in to prevent islanders from being left behind in the green transition, it is felt.

In the report, the Chief Officer for Assets and Infrastructure warns that “the current EV public network model is placing budget pressure on the Comhairle”. He notes, too, that “there is a risk that many areas within the Western Isles may not be commercially viable to install public EV infrastructure, and private investment may be difficult to attract. It is therefore essential that the Comhairle takes an active approach to the development and upkeep of EV infrastructure.”

However, expanding the public network across the islands comes with a hefty bill. Installing a single 50kW DC rapid charger in the Western Isles costs significantly more due to the higher transport logistics, contractor travel, and high grid connection expenses.

To maintain network coverage, the Comhairle is progressing Phase 2 plans between 2027 and 2030, delivering 4 AC fast chargers and 3 DC rapid chargers. 

The local strategy is “looking to develop four hub clusters in Lewis (Stornoway), Harris (Tarbert), Uist (Balivanich) & Barra (Castlebay)”, placing rapid chargers at key central intersections and connecting with mainland ferries.

The plans, though, also come at an environmental cost. Subsea distribution cables supplying Lewis, Harris, Uist, and Barra lack sufficient capacity to meet peak winter electricity demand.

Consequently, the business case admits that “right now, the energy supplying EV infrastructure in the partnership region is not fully clean and renewable”. 

The report says diesel generators at Battery Point and Arnish in Stornoway, and at Lochcarnan in South Uist, are being switched on to bolster supply during peak demand — meaning electric vehicles on island roads are currently partly powered by fossil‑fuel stations.

A 1.8GW subsea link between Arnish and Beauly is due to be completed by 2030 to unlock major offshore wind capacity, but local grid bottlenecks will remain a significant obstacle in the short to medium term.

Image content - library picture for illustration only