Two multi-million-pound regeneration projects in Uist and Vatersay are facing delays and governance hurdles, as council officers prepare to request funding deadline tweaks.
A progress report prepared by the Chief Executive for the Comhairle's Policy and Resources Committee meeting on Wednesday (23 September) reveals that two prominent capital initiatives, the £1.5m Uist Indoor 3G Project at Daliburgh in South Uist and the £2m Vatersay Harbour Marine Development Zone, are encountering planning, sustainability, and site issues.
According to the report, project leads have identified "areas of concern in relation to planning and sustainability" during the development of the Vatersay and 3G pitch projects.
Due to restrictions on the original 3G pitch site, work is underway to test a preferred alternative location, with full feasibility and sustainability results expected towards the end of the year.
Additionally, the scheduled availability of match funding opportunities has pushed projected completion dates beyond the UK Government's strict funding deadline.
The report highlights that "scheduled availability of match funding opportunities for both Vatersay and the 3G pitch contributes further to the forecast delay in delivery, which will be beyond the end March 2027 cut-off for commitment of funding."
As funding cannot be committed within the current financial year, officials must seek approval from Westminster to adjust the delivery plan.
The report notes the uncertainty around approval, stating: "As these projects are now unlikely to be able to commit funding in the current financial year, a change request will be submitted to the UK Government, and approval cannot be guaranteed."
Officers are recommending proactive financial management across the wider funding allocation.
Specifically, the Comhairle is being recommended to "note the change requests being submitted regarding the Uist Indoor 3G Project and Vatersay Harbour".
Councillors are also being asked to "agree that any underspend emerging within the programme be reallocated by the Chief Officer, Economic and Community Regeneration, in consultation with the Chief Executive and Chief Financial Officer, to address match funding gaps within other projects within the programme, or to supplement activity in relation to the roads and housing programmes, subject to the approval of UK Government."
Currently, only an in-principle request sits with the UK Government awaiting assessment of willingness to agree. Once delivery timescales are firmed up, a formal change request will follow.
Changes in national oversight further heighten pressure on delivery schedules.
The report points out that "the emergence of a new team within UKG responsible for monitoring of CRP delivery across the UK has highlighted the importance of delivery timescales for expenditure."
However, the report also notes that the UK Government "appears flexible in terms of change within the programme" and there is scope to move CRP funding across projects where approved.
Despite the setbacks in Vatersay and South Uist, there is good news on the broader £20.2m Community Regeneration Partnership (CRP) Fund, which comprises £20m in capital investment and £250k in revenue grant funding.
Progress continues to be made on a number of other Southern Isles projects that target connectivity, community resilience, and economic growth.
The single largest investment under the CRP is the £8.8m Uist & Barra Roads and Causeway Resilience Programme. Ground investigation and initial design work for the North Ford are nearing completion, with the Knockquien section at the most advanced stage as tenders prepare to go out to market in September.
However, officers note that larger and more complex road stretches, such as Kildonan, will require "more substantive investigation works including identification of land ownership" and are unlikely to get underway until Spring 2027, making it the final component of the roads programme.
Progress noted in other community projects by the report includes:
The £3.5m Outer Hebrides Housing Investment Fund is "anticipated to move into delivery shortly", pending a scheme of administration report to the Comhairle's Sustainable Development Committee next week before implementation.
The fund allocates £1m each for Empty Homes redevelopment and Energy Efficiency solutions.
Initial scoping for the £50,000 Isle of Barra Shared Space Childminding Pilot is complete, though the report highlights "current legislative restrictions of shared space childminding" and offers alternative options now being considered by multiple forums.
Match funding has been secured for two community-led projects from the Scottish Government's Regeneration Community Grant Fund (RCGF):
* £1.5m for Ionad Eilean na h-Òige (Comunn Eachdraidh Eirisgeidh)
* £1.5m for the Carinish Heritage Centre on North Uist.
Decisions from other funders remain pending. Both organisations anticipate moving into procurement at the end of the year, with construction works taking place in early 2027.
Other CRP-funded initiatives advancing include:
Ardveenish Harbour (£1m) — survey works complete, procurement for construction due in September.
West Camp (£500,000) — land acquisition from the Ministry of Defence underway, anticipated to conclude in Autumn, enabling commissioning of a Masterplan.
Isle of Barra - Shared Space Childminding Pilot (£50,000 revenue), scoping complete.
Western Isles CRP Project Development and Support (£200,000).